August
1. STRUCTURE – Upper Ground – 95% complete
结构-地上二层-完成95%
2. STRUCTURE – Precast all install LG panels
结构-地上一层-预制墙全部安装完毕
3. Gantry and Scaffold edge protection works
门架脚手架边缘加固完成
4. Services rough in works Basement B1 and B2 – Incl. Mech fans
地下室一层和二层各类管网正在安装
5. Civil works completed Warrigal Rd and now completing Dandenong Road.
Warrigal Road土石方作业完成,Dandenong一侧正在进行
6. Blockwork Basement commenced
地下室砌块墙开始施工