July
Lower ground transfer slab complete
Precast install LG panels
Upper ground Zone 1 and Zone 3 works
Services rough in works Basement B1 and B2
Powerline relocation works and Gantry Install
LG1 (Lower Ground Floor) 楼板浇筑完成,混凝土预制墙安装完毕
UG1(Upper Ground Level)区域1和3模板搭建,准备浇筑混凝土
地下室两层管道线缆正在铺设
Dandenong Road电线杆电缆重新布置
Dandenong Road门架搭建完毕