November
1. STRUCTURE – Building A – Framing to L3 nearing
completion, Pour 1 complete. Building B – Level 3
50% poured, Building C – L2 40% framed
结构-建筑A-三楼框架基本完成,1号混凝土浇筑完成。
建筑B-3楼混凝土浇筑完成50%。建筑C-二楼框架完成40%
2. SERVICES – Basement B1 and B2 HL services complete,
U/S and wall rough-in complete to LG apartments Building B
地下室B1和B2各类管网安装完毕,
建筑B-地上一层公寓天花板和墙面各类线缆安装完毕
3. FITOUT – Partitions framing to LG apartments complete,
Sheeting to top-strips 75%
地上一层间隔墙框架搭建完毕,石膏墙面板完成75%
4. Façade – Sub-framing to LG and townhouses commenced.
Frames due Early Nov
外立面-地上一层和联排别墅外立面底层支架开始安装
5. Precast procurement inline with structure pour dates
预制混凝土墙采购与现浇混凝土协调顺利